Permits, starts and completions describe different housing markets

A developer can receive a permit in March, break ground in June and finish a building the following year. The same project enters three statistics at different times. More completions alongside fewer permits can therefore describe a busy handover period and a thinner future pipeline.

Choose the milestone that answers the question

For current construction activity, begin with starts and units under construction. For newly completed supply, look at completions. Separate single-family and multifamily units before interpreting a sharp move: the start of one large apartment project can represent many units.